Peterborough showground plan of works

The East of England Showground have been carrying out a programme of works on the ground over 2014 which look to improve the conditions of the site for LAMMA's exhibitors and visitors.

The programme includes the installation of new roadside drainage, expanded roadways (using gravel to extend roadway widths) and also replaced / upgraded tarmac.

Some of the work in recent months has included:

October:

Grass Seed: Over seeding of the internal areas paying close attention to exposed areas and infilling with fresh soil.

French Drains: Digging out drains and filling with stone along road edges. 

Flushing of Land Drains: 3 days of onsite flushing of land drains with damaged drains being dug up and repaired.

November:

French Drains: Continued installation of roadside ‘French drains’

Repair / Replacement of Tarmac Roads: Repair and replacement of tarmac roadways with new tarmac applied to Dunblane Drive entrance and East Arena Roadway

New Roads: Installation of 2 new gravel style roadways in the West Car Park 
December:

Conclusion of works above.

View all Show news
Loading

"We had a busy stand right from the word go, visitors were engaged by what we had to show them. I think LAMMA has been re-established as a more comfortable, more accessible ‘must attend’ show." Adrian Winnett, Argo Tractors

How to get there

National Exhibition centre

Birmingham, B40 1NT, UK

 

 

Media partners

  • Farmers Guardian

Digital Media Partner

  • Farmers Guardian